Title: Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction, Inc. for the Liberty Trail Retaining Wall Project (SW26050)
Attachments: 1. Liberty_Trail_Retaining_Wall_CO_1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of:  08-18-26

 

Title:

title

Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction, Inc. for the Liberty Trail Retaining Wall Project (SW26050)

End

 

Background:

 The Liberty Trail Retaining Wall project will add a drainage structure and rebuild the wall west of Elm along the trail. This project will abut the OTA property and all safety procedures are in place. 

Change Order #1 addresses the following additions/deletions/changes to the contract:

-                     Add a water stop to the keyway to serve as an embedded waterproofing barrier.

-                     There is no change in contract time.

 

The total cost for Change Order #1 amounts to $3,040.00

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0

This Change Order(s):                                                               $3,040.00

Total Cost of Change Orders:                                          $3,040.00

Original Contract Amount:                                          $861,086.00

Revised Contract Amount:                                          $867,926.00

 

 

Percent Change in Contract:                                          0.79%

Applicable to Comp. Bid Act:                     0.79%

Cost:                                                                $3,040.00

Funding Source:                     Prop 6 and other various sources

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Liberty Trail Retaining wall CO 1

Recommendation:

recommend

Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction, Inc. for the Liberty Trail Retaining Wall project (SW26050)

 