Broken Arrow City Council
Meeting of: 04-05-2016
To: Mayor and City Council
From: Department of Engineering and Construction
Title:
title
Approval of the final acceptance of the public improvement (paving) for Access Optics, located at 2201 North Maple Avenue, Broken Arrow, Oklahoma
End
Background:
Cowen Construction completed construction of Access Optics, located at 2201 North Maple Avenue, Broken Arrow, Oklahoma. The required improvement is in accordance with approved construction plans and appropriate construction documents. This improvement was constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvement includes the following: (1) Paving.
The owner desires to donate the public improvement identified above to the City. This improvement has an approximate value of $8,081.49. Staff recommends that the Council approve the final acceptance of the public improvement.
Cost: $0
Prepared By: Jeff Bigby, P.E., Acting Director of Engineering and Construction
Reviewed By: Engineering and Construction Department
Finance Department
Assistant City Manager-Operations
Legal Department
Approved By: Michael L. Spurgeon, City Manager
Attachments: Detailed Assessment Breakdown
Recommendation:
Approve the final acceptance of the public improvement.