Approval of and authorization of Final Acceptance for the public improvements at Trails at Aspen Creek located at 2602 West Tucson Street
End
Background:
Triangle Construction and Utility, LLC has completed the construction for Trails at Aspen Creek project. The required improvements are in accordance with approved construction plans and appropriate construction documents. These improvements have been constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvements are for the sanitary sewer, storm, and water, and paving installations.
The owner desires to donate the public improvements identified above to the City of Broken Arrow. These improvements have an approximate value of $662,665.00
Cost: None
Funding Source: N/A
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Infrastructure Inventory - Trails at Aspen Creek
Recommendation:
recommend
Approve and authorize final acceptance and donation of the public improvements at Trails at Aspen Creek located at 2602 South Tucson Street