Acceptance of and authorization to accept the Change Order #1 for the South Park South Relief Line & Houston St Trenchless sanitary sewer rehabilitation (22600538)
End
Background:
The South Park South Project was put in place to Demo an existing lift station and install a liftstation. The project also included trenchless repair on two manholes to rectify a maintenance issue.
The project will need 71 additional days due to weather and utility complications.
The total cost for Change Order #1 amounts to $ (11,450.00)
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): ($11,450.00)
Total Cost of Change Orders: ($11,450.00)
Original Contract Amount: $789,310.00
Revised Contract Amount: $777,8602.00
Percent Change in Contract: (1.45%)
Applicable to Comp. Bid Act: 0%
Cost: $0
Funding Source: OWRB Loan
Requested By: Charlie Bright, P.E., Engineering and Construction Director
Approved By: City Manager’s Office
Attachments: South Park South Lift Station final CO
Recommendation:
recommend
Acceptance of and authorization to accept the Change Order #1 for the South Park South Relief Line & Houston St Trenchless sanitary sewer rehabilitation (22600538)