Approval of and authorization to execute Change Order No. 2 with Kimery Painting Inc for the Tiger Hill East Water Tank Restoration (2454460)
End
Background:
The Tiger Hill east water tank restoration project is to restore a 2 million gallon water tank. The tank was in disrepair and needed to be fixed and repainted. When the tank was emptied, it was found that the floor was in worse shape than anticipated. The floor welds need to be tested for strength and leaks. The center column was found to be in worse shape than originally thought as well. This needs to be repaired to ensure the integrity of the tank.
Change Order #2 addresses the following additions/deletions/changes to the contract:
- Additional Tank Repair for foam injection
- Coating tank floor due to additional tank repair
- Twenty-one Days for additional floor repair and fully blasting and coating floor.
The total cost for Change Order #2 amounts to $55,350.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $53,200.00
This Change Order(s): $55,350.00
Total Cost of Change Orders: $108,550.00
Original Contract Amount: $1,042,600.00
Revised Contract Amount: $1,151,150.00
Percent Change in Contract: 10.41%
Applicable to Comp. Bid Act: 2.80%
Cost: $55,350.00
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Tiger Hill Tank Change Order 2
Recommendation:
recommend
Approve and authorize execution of Change Order #2 with Kimery Painting Inc for the Tiger Hill East Water Tank Restoration (2454460)