Approval of and authorization to execute Change Order No. 1 with Timber Wolf Excavating, LLC for the Oak Crest Addition Sanitary Sewer and Water Line Improvements project (S.23070)
End
Background:
The Oak Crest addition Sanitary Sewer and Water Line Improvements project is rehabilitating the aging infrastructure throughout that neighborhood.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Install 240 LF of 12” HDPE sewer pipe on line 2, including up size casing pipe for creek crossing.
- Install additional 4’ drop manhole on line 2 with additional 4 ft of depth
- There is a 15-day change in contract time.
The total cost for Change Order #1 amounts to $61,228.40
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $61,228.40
Total Cost of Change Orders: $61,228.40
Original Contract Amount: $6,860,730.00
Revised Contract Amount: $6,921,958.40
Percent Change in Contract: 0.89%
Applicable to Comp. Bid Act: 0.77%
Cost: $61,228.40
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Change Order 1
Recommendation:
recommend
Approve and authorize execution of Change Order No. 1 with Timberwolf Excavating, LLC for the Oak Crest Sanitary Sewer and Water Line Improvements Project (S.23070)