Title: Approval of final acceptance of the public improvements for Broken Arrow Post-Acute Health Center
Attachments: 1. Broken Arrow Post Acute Health Infrastructure Inventory
Broken Arrow City Council
Meeting of: 07-07-2015
 
To:      Mayor and City Council
From:      Department of Engineering and Construction
Title:  
title
      Approval of final acceptance of the public improvements for Broken Arrow Post-Acute Health Center
End
 
Background:
D-Kerns Construction, Inc. has completed the construction of the Broken Arrow Post-Acute Health Center.  The required improvements are in accordance with approved construction plans and appropriate construction documents. These improvements were constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
 
Said Improvement includes the following:  (1) Storm Water; (2) Paving.
 
The owner desires to donate the public improvements identified above to the City.  These improvements have an approximate value of $269,739.00.
 
Cost:                   $0
 
Prepared By:             Douglas L. Tiffany, P.E., Director of Engineering and Construction
Reviewed By:            Finance Department
                  Assistant City Manager
 
Approved By:       Russell M. Gale, Acting City Manager
 
Attachments:            Detailed Assessment Breakdown
 
Recommendation:
Accept the Public Improvement: Storm Water and Paving.