Broken Arrow Drainage Advisory Committee
Meeting of: 04/28/25
Title:
title
Consideration, discussion, and possible action to recommend to City Council to expend funds to construct erosion control measures in the Bristol Ponds south detention pond and in the channel between Bristol Ponds and Elm Place (Case No 25-006)
End
Background:
The proposed project is near the Bristol Ponds subdivision located west of Elm Place and north of Washington St.
Staff investigated the site and found that the channel on both public and private does not appear to have been constructed per plan. It appears that erosive velocities were not mitigated. Erosion is present along the channel and the pond bank.
Bristol Ponds is a private subdivision platted in 2005. The City owns the channel between Bristol Ponds and Elm Place. The City also owns land south of the pond. The pond and its’ bank is privately owned.
Construction is anticipated to occur in the Summer of 2025.
Staff is requesting $230,000.00 of the 2018 GO Bond, Proposition 6 for construction costs.
This area flows to Haikey Creek.
Cost: $230,000.00
Funding Source: 2018 GO Bond, Proposition 6
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Drainage Report, Exhibits
Recommendation:
recommend
Recommend to City Council to expend funds to construct erosion control measures in the Bristol Ponds south detention pond and in the channel between Bristol Ponds and Elm Place.
end