Title: Approval of the Aspen Ridge Development September 2023 Update
Attachments: 1. Aspen Ridge September 2023 Update
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Economic Development Authority

Meeting of: 10-03-2023

 

Title:

title

Approval of the Aspen Ridge Development September 2023 Update

End

 

Background:

On July 31st, 2023, The Broken Arrow Economic Development Authority requested to be supplied with a monthly update of ongoing progress of the Aspen Ridge Development. Per the request, a meeting between Jennifer Rush, Economic Development Manager and a development representative of Oaktrust took place on September 26th, 2023 to obtain information on the attached progress for the month of September.

 

Cost:                                                                $0

Funding Source:                     N/A

Requested By:                      Jennifer Rush, Economic Development Manager

Approved By:                      City Manager’s Office

Attachments:                                          Aspen Ridge August Monthly Update

 

Recommendation:

recommend

Approve the Aspen Ridge September 2023 Update

end