Title: Acceptance of the Drainage Advisory Committee's recommendation to expend 2018 Go Bond, Proposition 6 funds for retaining an engineering consultant to design a set of construction plans for an updated outlet structure at 215 S Laurel Ave (Case No. 24-005)
Attachments: 1. 24-005 W Commercial
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 05/07/24

Title:
title
Acceptance of the Drainage Advisory Committee's recommendation to expend 2018 Go Bond, Proposition 6 funds for retaining an engineering consultant to design a set of construction plans for an updated outlet structure at 215 S Laurel Ave (Case No. 24-005)
End

Background:
The proposed project is at 215 S Laurel Avenue in Broken Arrow. The project will be to design an update to the pond outlet structure on a citizen's property.
In 2012, the City of Broken Arrow designed and constructed a project to extend a storm sewer from S Lewis Ave to the Creek behind 3321 W Commercial St. As a part of this project a new outfall was constructed on the pond to the south. The outfall was designed to release the water from pond at a rate equal to or less than the existing rate. An easement was not able to be acquired from the property owner to the west. Therefore, the outfall structure was moved 25 ft east and released in the channel behind 3321 W Commercial St.
The estimated design cost to engineer a repair and alteration of the outlet is approximately $30,000.00 in 2024 Dollars.
This area flows to Haikey Creek.
On April 29, 2024, the Drainage Advisory Committee reviewed and recommended to City Council to approve the request for $30,000.00 in 2018 GO Bond Proposition 6 funds for retaining an engineering consultant to design a set of construction plans for an updated outlet structure at 215 S Laurel Ave.


Cost: $30,000.00
Funding Source: 2018 GO Bond, Proposition 6
Requested By: Charlie Bright, Director of Engineering and Construction
Approved By: City Manager's Office
Attachments: Drainage Report, Exhibits


Recommendation:
recommend
Accept the Drainage Advisory Committees' recommendation to expend 2018 GO Bond Proposition 6 funds for retaining an engineering consultant to design a set of construction plans for an updated outlet structure at 215 S Laurel Ave.