Title: Approval of and authorization to execute Change Order No. 3 with Ascend Commercial Builders for the Broken Arrow Public Works Field Office Project (2217090)
Attachments: 1. CO3_Additional_Time_Trench_Drain
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of:  5-6-2025

 

Title:

title

Approval of and authorization to execute Change Order No. 3 with Ascend Commercial Builders for the Broken Arrow Public Works Field Office Project (2217090)

End

 

Background:

 The BA Public Works Field Office project is to renovate the building for field services personnel

Change Order #3 addresses the following additions/deletions/changes to the contract:

 

-                     To add a 20-day change in contract time due to lack of response on trench drain submittals. This held up plumbing work and inspections

 

 The total cost for Change Order #3 amounts to $0.00

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $131,173.86

This Change Order(s):                                                               $0.00

Total Cost of Change Orders:                                          $131,173.86

Original Contract Amount:                                          $1,700,314.98

Revised Contract Amount:                                          $1,831,488.84

 

Percent Change in Contract:                                          7.71%

Applicable to Comp. Bid Act:                     7.71%

Cost:                                                                $1,831,488.84

Funding Source:                     2018 GO Bond

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          BA Public Works Field Office Change Order 3
 

Recommendation:

recommend

Approve and authorize execution of Change Order #3 with Ascend Commercial Builders for the BA Public Works Field Office Project (2217090)