Approval of and authorization to execute the Change Order #1 with D-Kerns Construction, Inc. for the Melinda Park Pavement Rehab Project (ST22270)
End
Background:
The Melinda Park Project is to repair sidewalk, drive entrances and mill and overlay the roads in the Melinda Park Neighborhood.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- There was an undetectable water main leak that crews had to spend five days locating the source of the leak, which was causing damage to the roadway subgrade.
- The existing 15-inch reinforced concrete pipe storm drain crossing the roadway within the Melinda Park Subdivision has deteriorated and requires replacement.
The total cost for Change Order #1 amounts to $16,640.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $16,640.00
Total Cost of Change Orders: $16,640.00
Original Contract Amount: $2,658,490.00
Revised Contract Amount: $2,675,130.00
Percent Change in Contract: 0.63%
Applicable to Comp. Bid Act: 0.31%
Cost: $16,640.00
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Melinda Park Pavement Change Order 1
Recommendation:
recommend
Accept and authorize execution of Change Order #1 with D-Kerns Construction, Inc. for the Melinda Park Pavement Rehab Project (ST22270)
end