Title: Approval of and authorization to execute Change Order #1 with BJ’s Oil Field Construction Inc. for the Diocese Channel Stabilization (SW24080)
Attachments: 1. Diocese_Channel_Stabilization_Change_Order_1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 11-16-2026

 

Title:

title

Approval of and authorization to execute Change Order #1 with BJ’s Oil Field Construction Inc. for the Diocese Channel Stabilization (SW24080)

End

 

Background:

 The Diocese channel stabilization project is regrading the bank of the Diocese along Washington and adding a fleximat to provide erosion protection.

Change Order #1 addresses the following additions/deletions/changes to the contract:

-                     Final Reconciliation of quantities

o                     Removal of one tree

o                     1520 Additional SY of Sod

o                     Gripple Earth Percussion Anchors were Installed per supplier

o                     U-Anchors installed 

-                     There is a 0 day change in contract time.

 

 The total cost for Change Order #1 amounts to ($1582.00)

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0,000.00

This Change Order(s):                                                               ($1,582.00)

Total Cost of Change Orders:                                          ($1,582.00)

Original Contract Amount:                                          $295,115.00

Revised Contract Amount:                                          $293,533.00

 

Percent Change in Contract:                                          -0.54%

Applicable to Comp. Bid Act:                     0.0%

Cost:                                                                ($1,582.00)

Funding Source:                     2018 GO Bond Funds

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Diocese Channel Stabilization Change Order 1
 

Recommendation:

recommend

Approval of and authorization to execute Change Order #1 with BJ’s Oil Field Construction Inc. for the Diocese Channel Stabilization (SW24080)