Broken Arrow City Council
Meeting of: 11-16-2026
Title:
title
Approval of and authorization to execute Change Order #1 with BJ’s Oil Field Construction Inc. for the Diocese Channel Stabilization (SW24080)
End
Background:
The Diocese channel stabilization project is regrading the bank of the Diocese along Washington and adding a fleximat to provide erosion protection.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Final Reconciliation of quantities
o Removal of one tree
o 1520 Additional SY of Sod
o Gripple Earth Percussion Anchors were Installed per supplier
o U-Anchors installed
- There is a 0 day change in contract time.
The total cost for Change Order #1 amounts to ($1582.00)
The additional cost associated with these changes is as follows:
Previous Change Orders: $0,000.00
This Change Order(s): ($1,582.00)
Total Cost of Change Orders: ($1,582.00)
Original Contract Amount: $295,115.00
Revised Contract Amount: $293,533.00
Percent Change in Contract: -0.54%
Applicable to Comp. Bid Act: 0.0%
Cost: ($1,582.00)
Funding Source: 2018 GO Bond Funds
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Diocese Channel Stabilization Change Order 1
Recommendation:
recommend
Approval of and authorization to execute Change Order #1 with BJ’s Oil Field Construction Inc. for the Diocese Channel Stabilization (SW24080)
end