Title: Approval of and authorization to execute Change Order No. 3 with Crossland Heavy Construction for the Lynn Lane Waste Water Treatment Plant Disinfection Improvements (S1905)
Attachments: 1. CO No. 3- Emergency By-Pass System
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of:  03-18-2025

 

Title:

title

Approval of and authorization to execute Change Order No. 3 with Crossland Heavy Construction for the Lynn Lane Waste Water Treatment Plant Disinfection Improvements (S1905)

End

 

Background:

 The LLWWTP Disinfection system improvements project is nearly complete and needs the following Change order to properly get the system working for that we can achieve substantial completion.

Change Order #3 addresses the following additions/deletions/changes to the contract:

-                     Purchase and installation of a new Actuator

 

-                     14 days in added time.

 

 The total cost for Change Order #3 amounts to $51,400.21

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          ($11,138.16)

This Change Order(s):                                                               $51,400.21

Total Cost of Change Orders:                                          $40,262.05

Original Contract Amount:                                          $5,841,000.00

Revised Contract Amount:                                          $5,881,262.05

 

Percent Change in Contract:                                          0.68%

Applicable to Comp. Bid Act:                     0.88%

Cost:                                                                $5,881,262.05

Funding Source:                     2018 GO Bond

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Emergency by-pass system CO 3 

Recommendation:

recommend

Approve and authorize execution of Change Order #3 with Crossland Heavy Contractors for the Lynn Lane Waste Water Treatment Plant Disinfection Improvements (S1905)

end