Broken Arrow City Council
Meeting of: 03-18-2025
Title:
title
Approval of and authorization to execute Change Order No. 3 with Crossland Heavy Construction for the Lynn Lane Waste Water Treatment Plant Disinfection Improvements (S1905)
End
Background:
The LLWWTP Disinfection system improvements project is nearly complete and needs the following Change order to properly get the system working for that we can achieve substantial completion.
Change Order #3 addresses the following additions/deletions/changes to the contract:
- Purchase and installation of a new Actuator
- 14 days in added time.
The total cost for Change Order #3 amounts to $51,400.21
The additional cost associated with these changes is as follows:
Previous Change Orders: ($11,138.16)
This Change Order(s): $51,400.21
Total Cost of Change Orders: $40,262.05
Original Contract Amount: $5,841,000.00
Revised Contract Amount: $5,881,262.05
Percent Change in Contract: 0.68%
Applicable to Comp. Bid Act: 0.88%
Cost: $5,881,262.05
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Emergency by-pass system CO 3
Recommendation:
recommend
Approve and authorize execution of Change Order #3 with Crossland Heavy Contractors for the Lynn Lane Waste Water Treatment Plant Disinfection Improvements (S1905)
end