Broken Arrow City Council
Meeting of: 6-16-2025
Title:
title
Approval of and authorization to execute Change Order No. 3 with Becco Contractors Inc for the Houston St Widening (ST2028)
End
Background:
The Houston st Widening Project is to widen and improve Houston St from Garnett to Olive Ave. Storm box improvements, utility relocation, and entrance improvements are all part of this project.
Change Order #3 addresses the following additions/deletions/changes to the contract:
- SX2020 Geogrid to stabilize the south side of the road due to soft subgrade. This makes sure that the road will be stable and minimizes the chances of potholing and ruts
- Additional survey to correct missing information from the original survey.
- There is a 7 day change in contract time.
The additional cost associated with these changes is as follows:
Previous Change Orders: $33,250.00
This Change Order(s): $47,500.00
Total Cost of Change Orders: $80,750.00
Original Contract Amount: $5,718,000.00
Revised Contract Amount: $5,798,750.00
Percent Change in Contract: 1.39%
Applicable to Comp. Bid Act: 1.39%
Cost: $47,500.00
Funding Source: 2018 GO Bond Funds
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Change order #3 Houston St Widening
Recommendation:
recommend
Approval of and authorization to execute Change Order #3 with Becco Contractors Inc for the Houston St Widening (ST2028)
end