Title: Consideration, discussion and possible action to recommend to City Council to expend funds to design drainage design improvements from 3729 South 195th East Avenue to East 37th Court South (Case No. 26-002)
Attachments: 1. 26-002 DAC Packet - 3729 S 195th Steeple Chase
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Drainage Advisory Committee

Meeting of: 02-23-2026

 

Title:

title

Consideration, discussion and possible action to recommend to City Council to expend funds to design drainage design improvements from 3729 South 195th East Avenue to East 37th Court South (Case No. 26-002)

End

 

Background:

The project at 3729 South 195th East Ave. is currently in design for drainage improvements of the existing drainage system. The project is redirecting most of the storm runoff underground with a shallow grassed overflow channel.

Stormwater flows from E 37th Ct. to the inlet by means of a concrete channel in an easement across 4 properties. The concrete channel leading to the inlet has a history of maintenance concerns.

Staff requested $35,000.00 of the 2018 GO Bond, Proposition 6 for design costs at the 07-29-2024 Drainage Advisory Committee Meeting (Case Number 24-011) and was recommended for approval. Council approved the recommendation on 08-20-2024.

A contract with Cross Timbers Consulting was executed for a total amount of $42,755.00 by Council on 05-20-2025. Staff is requesting an additional $7,755.00 of the 2018 General Obligation Bond Proposition 6 funds to cover the design contract amount. 

This area flows to Spunky Creek.

 

Cost:                                                                $7,755.00

Funding Source:                     2018 General Obligation Bond, Proposition 6

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Drainage Report, Exhibits   

 

Recommendation:

recommend

Recommend to City Council the expenditure of $7,755.00 for additional funds to design drainage improvements from 3729 South 195th East Ave to East 37th Court South (Case No. 26-002)end