Broken Arrow City Council
Meeting of: 09-01-26
Title:
title
Approval of and authorization to execute Change Order #1 with Builders Unlimited for the Kenosha Street Sidewalks project (ST23290)
End
Background:
The Kenosha Street sidewalks project installed sidewalks along Kenosha from mid mile west to tie into the sidewalks west of the rail road tracks.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Final Reconciliation of the line items.
- There is no change in contract time.
The total cost for Change Order #1 amounts to $5,530.71
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $5,530.71
Total Cost of Change Orders: $5,530.71
Original Contract Amount: $324,239.76
Revised Contract Amount: $329,770.47
Percent Change in Contract: 1.71%
Applicable to Comp. Bid Act: 0.0%
Cost: $5,530.71
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Kenosha S Sidewalks Final Reconciliation CO 1
Recommendation:
recommend
Approval of and authorization to execute Change Order #1 with Builders Unlimited for the Kenosha St Sidewalks project (ST23290)
end