Broken Arrow City Council
Meeting of: 04-21-26
Title:
title
Approval of and authorization to execute Change Order No. 3 with Myers-Cherry Construction, LLC for the Operations Center Administration Building Renovation (2317210)
End
Background:
The Operations Center Administration building renovation project renovates the streets and stormwater facility to house the administration personnel for Utilities and Streets and Stormwater.
Change Order #3 addresses the following additions/deletions/changes to the contract:
- Change Order #3 is in regards to PR 007: Upper Roof Wall Panel Replacement. The scope of work includes removal of existing wall panels, metal stud infill, sheathing, fluid-applied vapor barrier, hat channel install, roof blocking, new metal panels, sheet metal flashing, and trims.
- Total cost of the Change Order is $76,901.00. However, owner contingency will cover $17,736.37. This brings the Change Order cost to $59,164.53. This also includes 10% markup as well.
- This will add 10 Days in project time
The total cost for Change Order #3 amounts to $59,164.63
The additional cost associated with these changes is as follows:
Previous Change Orders: $167,220.70
This Change Order(s): $59,164.63
Total Cost of Change Orders: $226,385.33
Original Contract Amount: $2,347,500.00
Revised Contract Amount: $2,573,885.33
Percent Change in Contract: 9.64%
Applicable to Comp. Bid Act: 9.64%
Cost: $59,164.63
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Change Order 3 Upper Roof Wall Panel Replacement
Recommendation:
recommend
Approval of and authorization to execute Change Order #3 with Myers-Cherry Construction, LLC for the Operations Center Administration Building Renovation (2317210)
end