File #: 15-637    Name:
Type: Consent Item Status: Passed
File created: 11/3/2015 In control: Broken Arrow City Council
On agenda: 11/9/2015 Final action: 11/9/2015
Title: Approval of and authorization to execute Earth Change Pay Request Number 3 for Tri-Star Construction, LLC through the Vision 2025 Sales Tax Program in association with the Stoney Creek Hotel and Conference Center
Attachments: 1. Pay Req#3 Fully Signed.pdf

Broken Arrow City Council

                                                                                               Meeting of: 11-09-2015

                                                                                    

To:                     Mayor and City Council

From:                     Development Services Department

Title: 

title

                     Approval of and authorization to execute Earth Change Pay Request Number 3 for Tri-Star Construction, LLC through the Vision 2025 Sales Tax Program in association with the Stoney Creek Hotel and Conference Center

End

Background:

Stoney Creek Hospitality is requesting partial payment of the Earth Change construction for Tri-Star Construction, LLC related to the Stoney Creek Hotel and Conference Center.  The attached documents reference to Earth Change pay request number 3 from Cowan Group Engineering, LLC.

City staff has reviewed the pay request and recommends approval.  Payment will be through the Vision 2025 sales tax program.  The draw amount is $750,347.81 and will be deducted from the contract bid amount of 1,815,033.50.  Total draws to date is $1,665,892.30.

 

Cost:                      $750,347.81 (from Vision 2025 Funds for Earth Change Contract Bid amount of $1,815,033.50)

Prepared By:                                           Michael Skates, P.E., CFM, Development Services Director

Reviewed By:                                          Engineering and Construction Department
                                    Finance Department
                                    Legal Department
                                    Assistant City Manager

Approved By:                      Michael L. Spurgeon, City Manager
                                                                 

Attachments:                                          Earth Change Pay Request No. 3 Documents

Recommendation
:

Approve Earth Change Pay Request Number 3 for Tri-Star Construction, LLC.