Broken Arrow City Council
Meeting of: 11-05-2024
Title:
title
Consideration, discussion, and possible award of the lowest responsible bid to Ellis Concrete Construction, LLC and approve and authorize execution of a construction contract for Concrete Panel Replacement Street Repair - Brentwood (Project No. ST23300)
End
Background:
Design for the Concrete Panel Replacement Street Repair for the Brentwood subdivision has been completed and Engineering and Construction Department staff worked with the design consultant to prepare construction documents for letting. The project includes the removal and rehabilitation of approximately 12,000 square yards of concrete roadway panels along with miscellaneous concrete work including sidewalk, curb, sewer, and ADA ramps. This roadway reconstruction will be located in the Brentwood subdivision between Washington Street & New Orleans Street and between Olive Avenue & Aspen Avenue.
The project was advertised for bids on September 24, 2024, and October 1, 2024. Bids were opened on October 15, 2024, and five (5) bids were received. The Certified Bid Tabulation is attached. The bids submitted were composed of nineteen (19) pay items.
The lowest responsible bid was submitted by Ellis Concrete Construction, LLC for $1,249,907.50. The engineer’s estimate was $1,409,710.00.
Cost: $1,249,907.50
Funding Source: 2018 GO Bond - Residential Rehab Project
Requested By: Charlie Bright, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Certified Bid Tabulation
Recommendation:
recommend
Award the lowest responsible bid to Ellis Concrete Construction, LLC and approve and authorize execution of a construction contract for Concrete Panel Replacement Street Repair - Brentwood (Project No. ST23300).
end