Broken Arrow City Council
Meeting of: 12-02-2025
Title:
title
Approval of and authorization to execute the Change Order No. 1 with Northeastern Irrigation & Landscape, Inc for the Broken Arrow Gateways Entry Signage (22502158)
End
Background:
The Broken Arrow Gateways Entry Signage project added new entry signs at the boundary of the City of Broken Arrow.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- No Changes in the work, but amending the final contract amount
- There is a 22 day change in contract time.
The total cost for Change Order #1 amounts to $13,568.27
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): ($147,617.84)
Total Cost of Change Orders: ($147,617.84)
Original Contract Amount: $819,207.65
Revised Contract Amount: $671,589.81
Percent Change in Contract: -18.02%
Applicable to Comp. Bid Act: 0.0%
Cost: $-147,617.84
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: CO 01 Gateways Entry Signage
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Northeastern Irrigation & Landscape, Inc, LLC for the Broken Arrow Gateways Entry Signage (22502158)
end