Approval of and authorization to execute Change Order No. 1 with Myers-Cherry Construction, LLC for the Operations Center Administration Building Renovation (2317210)
End
Background:
The Operations Center Administration building renovation project renovates the streets and stormwater facility to house the administration personnel for Utilities and Streets and Stormwater.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- To correct verbiage in the contract to allow for the correct number of working days.
Total time added to contract is:
- 100 Days
The total cost for Change Order #1 amounts to $32,143.50
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $0
Total Cost of Change Orders: $0
Original Contract Amount: $2,347,500.00
Revised Contract Amount: $N/A
Percent Change in Contract: 0%
Applicable to Comp. Bid Act: 0%
Cost: $0
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Time Adjustment CO 1
Recommendation:
recommend
Approval of and authorization to execute Change Order #1 with Myers-Cherry Construction, LLC for the Operations Center Administration Building Renovation (2317210)