Title: Approval of and authorization to execute Change Order No. 1 with Myers-Cherry Construction, LLC for the Operations Center Administration Building Renovation (2317210)
Attachments: 1. Change_Order__1_Addition_of_Time
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of:  12-02-2025

 

Title:

title

Approval of and authorization to execute Change Order No. 1 with Myers-Cherry Construction, LLC for the Operations Center Administration Building Renovation (2317210)

End

 

Background:

 The Operations Center Administration building renovation project renovates the streets and stormwater facility to house the administration personnel for Utilities and Streets and Stormwater.  

Change Order #1 addresses the following additions/deletions/changes to the contract:

-                     To correct verbiage in the contract to allow for the correct number of working days.

Total time added to contract is:

-                     100 Days

 

 The total cost for Change Order #1 amounts to $32,143.50

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0

This Change Order(s):                                                               $0

Total Cost of Change Orders:                                          $0

Original Contract Amount:                                          $2,347,500.00

Revised Contract Amount:                                          $N/A

 

Percent Change in Contract:                                          0%

Applicable to Comp. Bid Act:                     0%

Cost:                                                                $0

Funding Source:                     2018 GO Bond

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Time Adjustment CO 1
 

Recommendation:

recommend

Approval of and authorization to execute Change Order #1 with Myers-Cherry Construction, LLC for the Operations Center Administration Building Renovation (2317210)