Broken Arrow Municipal Authority
Meeting of: 06-02-2025
Title:
title
Approval of and authorization to execute Change Order No. 1 with Landmark Structures for the New Elevated Water Storage Tank (165424)
End
Background:
The New Elevated Storage Tank project is to add a 2.5 Million Gallon storage tank in south Broken Arrow. The project needs the following Change order to account for the extra material it took to build the road. The road into the tank is part of the project and would not “heal” during initial construction. Geogrid and rock were added to make road drivable. The road has healed after a water leak was discovered.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- 780 CY of road remediation and stabilization to include Geogrid, crusher run, and
- 15 days in added time.
The total cost for Change Order #1 amounts to $54,600.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $54,600.00
Total Cost of Change Orders: $54,600.00
Original Contract Amount: $10,722,844.00
Revised Contract Amount: $10,777,444.00
Percent Change in Contract: 0.51%
Applicable to Comp. Bid Act: 0.0%
Cost: $10,777,444.00
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Landmark 1849 CO 1
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Landmark Structures for the New Elevated Storage Tank Project (165424).
end