Skip to main content
LEGISLATIVE RESEARCH CENTER
File #: 24-851    Name:
Type: Consent Item Status: Agenda Ready
File created: 6/21/2024 In control: Broken Arrow Municipal Authority
On agenda: 7/15/2024 Final action:
Title: Award the lowest responsible bid to Core & Main, LP for construction materials for the Old Town Waterline Improvements (Project No. 2254400)
Attachments: 1. Bid Tabulation - Dallas 2nd to 5th St. Old Town Waterline
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of: 07-15-2024

 

Title:

title

Award the lowest responsible bid to Core & Main, LP for construction materials for the Old Town Waterline Improvements (Project No. 2254400)

End

 

Background:

In the 2020 Old Town Water System Improvements Engineering Report, Garver identified over 30 water line projects where we are replacing 100+ year-old cast-iron pipe to improve water quality, volume, and fire flows.  Some of these projects are combined during design and construction and others sometime stand alone.  Anything we do that falls under the “Old Town Water” which has been funded under loan project number 2254400.  

The project Dallas Street from 2nd to 5th Street Waterline was advertised in May and June 2024. There were four (4) bids received on June 2024. The bids are attached.  The lowest responsible bidder was Core & Main, LP for a Base Bid of $67,538.20.

 

Cost:                                                                $67,538.20

Funding Source:                     OWRB Loan

Requested By:                      Timothy Robins, P.E., CWI, CFM, Director of Utilities

Approved By:                      City Manager’s Office

Attachments:                                          Bid Tabulation for Dallas Street from 2nd to 5th Street - Old Town Waterline Improvements

 

Recommendation:

recommend

Award the lowest responsible bid to Core & Main, LP for construction materials for the Old Town Waterline Improvements (Project No. 2254400) 

end