File #: 25-1149    Name:
Type: Consent Item Status: Agenda Ready
File created: 8/6/2025 In control: Broken Arrow City Council
On agenda: 8/19/2025 Final action:
Title: Approval of and authorization to execute Change Order No. 2 with Gober Construction LLC for the Concrete Panel Replacement Turtle Creek Phase 2 (ST23030)
Attachments: 1. Turtle_Creek_Change_Order___2
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of:  08-19-2025

 

Title:

title

Approval of and authorization to execute Change Order No. 2 with Gober Construction LLC for the Concrete Panel Replacement Turtle Creek Phase 2 (ST23030)

End

 

Background:

 The Concrete Panel Replacement Turtle Creek Phase 2 project is to rehabilitate the neighborhood concrete streets. 

Change Order #2 addresses the following additions/deletions/changes to the contract:

-                     To amend the final contract amount adding additional driveways, concrete panels, storm inlet and moved a fire hydrant.

.

 

 The total cost for Change Order #2 amounts to $6000.00

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $6000.00

This Change Order(s):                                                               $51,381.50

Total Cost of Change Orders:                                          $57,381.50

Original Contract Amount:                                          $525,489.00

Revised Contract Amount:                                          $582,870.50

 

Percent Change in Contract:                                          10.92%

Applicable to Comp. Bid Act:                     1.14%

Cost:                                                                $51,381.50

Funding Source:                     STCI

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Turtle Creek Phase 2 CO 2 and backup documentation
 

Recommendation:

recommend

Approval of and authorization to execute Change Order #2 with Gober Construction LLC for the Concrete Panel Replacement Turtle Creek Phase 2 (ST23030)