Broken Arrow City Council
Meeting of: 11-19-2024
Title:
title
Approval of and authorization to execute Change Order No. 1 with Mowtown Outdoors for the Gardens at Central Park (2360450)
End
Background:
The Gardens at Central Park will add a Rose Garden to the Rose District. This project will beautify the area and provide a landscaped area to visit and refelect
Change Order No. 1 addresses the following additions/deletions/changes to the contract:
- To add a pergola to the project
- There is no change in contract time.
The total cost for Change Order No. 1 amounts to $10,000.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $10,000.00
Total Cost of Change Orders: $10,000.00
Original Contract Amount: $467,793.00
Revised Contract Amount: $477,793.00
Percent Change in Contract: 2.14%
Applicable to Comp. Bid Act: 2.14%
Cost: $477,793.00
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Garden at Central Park CO 1
Recommendation:
recommend
Approve and authorize execution of Change Order No. 1 with Mowtown Outdoors for the Gardens at Central Park (2360450)
end