Approval of and authorization of Final Acceptance for the public improvements at Village at Southern Trails II located south of New Orleans between Olive and Aspen
End
Background:
Timber Wolf Excavating, LLC has completed the construction for the Village at Southern Trails II Subdivision project. The required improvements are in accordance with approved construction plans and appropriate construction documents. These improvements have been constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvements are for the water, sanitary, storm and paving installations.
The owner desires to donate the public improvements identified above to the City of Broken Arrow. These improvements have an approximate value of $3,131,184.15
Cost: $0
Funding Source: N/A
Requested By: Ethan JL Edwards, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: COBA Infrastructure Inventory - Village at Southern Trails II
Recommendation:
recommend
Approve and authorization for final acceptance and donation of the public improvements at Village at Southern Trails II located south of New Orleans between Olive and Aspen
end