Title:
title
Approval of and authorization to execute Change Order No. 1 with Ira M. Green Construction for the Highland Park Rugby Fields (22501871)
End
Background:
The Highland Park Rugby Field project took an open field that was not maintained and turned it into a parking lot, rugby field with posts, and a sprinkler system. This field will allow for the sport of rugby to grow in Oklahoma.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Request to extend the contract time due to weather conditions and vendor delays due to sod availability.
The total cost for Change Order #1 amounts to $0
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $0
Total Cost of Change Orders: $0
Original Contract Amount: $705,770.00
Revised Contract Amount: $705,770.00
Percent Change in Contract: 0%
Applicable to Comp. Bid Act: 0%
Cost: $0
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Highland Park Rugby Field Time Change Order
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Ira M. Green Construction for the Highland Park Rugby Fields (22501871)