Skip to main content
LEGISLATIVE RESEARCH CENTER
File #: 25-1338    Name:
Type: General Business Status: Agenda Ready
File created: 9/15/2025 In control: Broken Arrow City Council
On agenda: 10/7/2025 Final action:
Title: Consideration, discussion, and possible approval of and authorization to award the lowest responsible bid to Myers-Cherry Construction, LLC, and approve and authorize execution of construction contract for Operations Center Administration Building Project (Project No. 2317210)
Attachments: 1. 09252025_-_Bid_Tab.Signed - 2317210
Broken Arrow City Council
Meeting of: 10-07-2025

Title:
title
Consideration, discussion, and possible approval of and authorization to award the lowest responsible bid to Myers-Cherry Construction, LLC, and approve and authorize execution of construction contract for Operations Center Administration Building Project (Project No. 2317210)

End

Background:
Throughout 2022, a space needs assessment study was performed on departments across the city government to determine the best utilization of facility resources for the growing work force. This renovation project is based on those findings, combining the administration of the Utilities department with Streets and Stormwater administration. The neighborhood engagement inspections division out of Community Development will also remain within the facility.

The project was advertised on August 28, 2025 and September 4, 2025. A mandatory Pre-Bid meeting was held on September 4, 2025 and September 11, 2025. There were four (4) bids received on September 25, 2025. The Certified Bid Tabulation is attached. This project included a base bid to renovate the interior portion of the facility, add windows, upgrade MEP systems, and finishes; Alternate 1: to add a covered canopy at the front entry; and Alternate 2: a $40,000 contingency allowance, along with an $18,500 building signage allowance. The base bid and all alternates are recommended to be awarded. The lowest responsible bid for these items was from Myers-Cherry Construction, LLC for $2,282,500.00. The Architects' estimate for these items was $3,038,910.55.

Cost: $2,282,500.00
Funding Source: 2018 GO Bond and STCI
Requested By: Charlie Bright, Director of Engineering & Construction
Approved By: City Manager's Office
Attachments: Operations Center - Administration Building Certified Bid Tabulation

Recommendation:
recommend
Approval and authorization to award the lowest responsible bid to Myers-Cherry Construction, LLC, and approve and authorize execution ...

Click here for full text