Title: Approval of and authorization to execute Change Order No. 1 with Gober Construction LLC for the East Natchez St and 8th St Culvert Replacement (SW21020)
Attachments: 1. Signed CO1 - Natchez culvert
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of:  09-02-2025

 

Title:

title

Approval of and authorization to execute Change Order No. 1 with Gober Construction LLC for the East Natchez St and 8th St Culvert Replacement (SW21020)

End

 

Background:

 The East Natchez St and 8th St Culvert Replacement project is to repair 3 -48” culverts under E Natchez St. This culvert passes the water from the golf course into a concrete channel. The current channel has eroded and undermined the road. This project will remedy the issues created by the undermining 

Change Order #1 addresses the following additions/deletions/changes to the contract:

  • Lower 6” PVC Water line and encase it in 14” steel.
  • Install additional 43x26” pipe due to being removed to lower water line.
  • Remove and Replace Pavement Due to being unstable. Remove and Replace Concrete curb

Total time added to contract is:

  • 5 Days

 

 The total cost for Change Order #1 amounts to $32,143.50

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0

This Change Order(s):                                                               $32,143.50

Total Cost of Change Orders:                                          $32,143.50

Original Contract Amount:                                          $324,821.90

Revised Contract Amount:                                          $356,965.40

 

Percent Change in Contract:                                          9.90%

Applicable to Comp. Bid Act:                     5.23%

Cost:                                                                $32,143.50

Funding Source:                     Prop 6

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          East Natchez St and 8th St Culvert Replacement CO 1
 

Recommendation:

recommend

Approval of and authorization to execute Change Order #1 with Gober Construction LLC for the East Natchez St and 8th St Culver Replacement (SW21020)

end