Broken Arrow City Council
Meeting of: 09-02-2025
Title:
title
Approval of and authorization to execute Change Order No. 1 with Gober Construction LLC for the East Natchez St and 8th St Culvert Replacement (SW21020)
End
Background:
The East Natchez St and 8th St Culvert Replacement project is to repair 3 -48” culverts under E Natchez St. This culvert passes the water from the golf course into a concrete channel. The current channel has eroded and undermined the road. This project will remedy the issues created by the undermining
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Lower 6” PVC Water line and encase it in 14” steel.
- Install additional 43x26” pipe due to being removed to lower water line.
- Remove and Replace Pavement Due to being unstable. Remove and Replace Concrete curb
Total time added to contract is:
The total cost for Change Order #1 amounts to $32,143.50
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $32,143.50
Total Cost of Change Orders: $32,143.50
Original Contract Amount: $324,821.90
Revised Contract Amount: $356,965.40
Percent Change in Contract: 9.90%
Applicable to Comp. Bid Act: 5.23%
Cost: $32,143.50
Funding Source: Prop 6
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: East Natchez St and 8th St Culvert Replacement CO 1
Recommendation:
recommend
Approval of and authorization to execute Change Order #1 with Gober Construction LLC for the East Natchez St and 8th St Culver Replacement (SW21020)