Broken Arrow City Council
Meeting of: 06-15-2026
Title:
title
Approval of and authorization to execute the Change Order #2 with Cherokee Pride Construction, Inc. for the Carriage Crossing Residential Rehab Project (ST25310)
End
Background:
The Carriage Crossing Residential Rehab project is to improve the residential roads to be fixed. Roughly half of the project was asphalt streets while the other half is concrete. The project will also address some driveway and sidewalk issues.
Change Order #2 addresses the following additions/deletions/changes to the contract:
- This Change Order reconciles what was installed in the field. There was more damage than originally thought and more panels needed to be replaced. Drainage valley gutters needed to be replaced and steep curb openings needed to be installed.
- There is a 18 day change in contract time.
The total cost for Change Order #2 amounts to $174,267.60
The additional cost associated with these changes is as follows:
Previous Change Orders: $40,000.00
This Change Order(s): $174,267.60
Total Cost of Change Orders: $214,267.60
Original Contract Amount: $1,427,226.75
Revised Contract Amount: $1,641,494.35
Percent Change in Contract: 15.01%
Applicable to Comp. Bid Act: 2.80%
Cost: $174,267.60
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Carriage Crossing Change Order 2
Recommendation:
recommend
Approve and authorize execution of Change Order #2 with Cherokee Pride Construction, Inc. for the Carriage Crossing Residential Rehab Project (ST25310)
end