Broken Arrow City Council
Meeting of: 03-18-2025
Title:
title
Approval of and authorization to execute Change Order No. 1 with Kimery Painting Inc for the Tiger Hill East Water Tank Restoration (2454460)
End
Background:
The Tiger Hill east water tank restoration project is to restore a 2 million gallon water tank. The tank was in disrepair and needed to be fixed and repainted. When the tank was emptied, it was found that the floor was in worse shape than anticipated. The floor welds need to be tested for strength and leaks. The center column was found to be in worse shape than originally thought as well. This needs to be repaired to ensure the integrity of the tank.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Cost associated with the testing and coating of floor weld seams
- Engineering Cost
- Additional Tank Bracing
- Deduction for not coating tank floor
- Twenty-one Days for column repairs and weld tasting.
The total cost for Change Order #1 amounts to $53,200.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $53,200.00
Total Cost of Change Orders: $53,200.00
Original Contract Amount: $1,042,600.00
Revised Contract Amount: $1,095,800.00
Percent Change in Contract: 5.10%
Applicable to Comp. Bid Act: 2.80%
Cost: $1,095,800.00
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Tiger Hill Tank Change Order 1
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Kimery Painting Inc for the Tiger Hill East Water Tank Restoration (2454460)
end