Legislation Details

File #: 26-695    Name:
Type: Consent Item Status: Agenda Ready
File created: 5/13/2026 In control: Broken Arrow City Council
On agenda: 5/19/2026 Final action:
Title: Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction Inc. for the 2025 Portland Cement Concrete Street Repair Project (25.175)
Attachments: 1. PCC_CHANGE_ORDER_1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 05-19-2026

 

Title:

title

Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction Inc. for the 2025 Portland Cement Concrete Street Repair Project (25.175)

End

 

Background:

The Portland Cement Concrete (PCC) Street Repair project is a three-year contract. This contract allows for the repairs of streets, sidewalks, drives, and other concrete structures that City crews do not otherwise have the time and resources to complete in house.   

Change Order #1 addresses the following additions/deletions/changes to the contract:

-                     Add money to the original contract to cover larger work orders. These funds are provided by the departments/divisions that are requesting the work orders to be accomplished. 

Total time added to contract is:

-                     0.

 

 The total cost for Change Order #1 amounts to $3,090,956.41

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0

This Change Order(s):                                                               $3,090,956.41

Total Cost of Change Orders:                                          $3,090,956.41

Original Contract Amount:                                          $671,750.00

Revised Contract Amount:                                          $3,762,706.41

 

Percent Change in Contract:                                          460.13%

Applicable to Comp. Bid Act:                     0%

Cost:                                                                $3,090,956.41

Funding Source:                     Mulitple (as needed)

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          PCC Change order 1
 

Recommendation:

recommend

Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction Inc. for the 2025 Portland Cement Concrete Street Repair Project (25.175)

end