LEGISLATIVE RESEARCH CENTER
File #: 16-101    Name:
Type: Consent Item Status: Passed
File created: 1/25/2016 In control: Broken Arrow City Council
On agenda: 2/2/2016 Final action:
Title: Approval of PT15-116, Conditional Final Plat, Collision Works, a Replat of Steele Morrel Center, 2 lots, 2.64 acres, CH to PUD 243/CH and IL, southeast corner of Kenosha Street and 14th Street , south of Kenosha Street, one-third mile east of 9th Street
Attachments: 1. 1-FAC.BDM.01-04-2016.pdf, 2. 2-CHECKLIST.COLLISION WORKS.pdf, 3. 3-CONDITIONAL FINAL PLAT.COLLISION WORKS.pdf, 4. 4-CONCEPTUAL SITE PLAN.COLLISION WORKS.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 02-02-2016

 

To:                     Mayor and City Council Members

From:                     Development Services Department

Title: 

title

                     Approval of PT15-116, Conditional Final Plat, Collision Works, a Replat of Steele Morrel Center, 2 lots, 2.64 acres, CH to PUD 243/CH and IL, southeast corner of Kenosha Street and 14th Street , south of Kenosha Street, one-third mile east of 9th Street

End

Background:

 The conditional final plat of Collision Works contains 2.64 acres located on the southeast corner of Kenosha Street and 14th Street, south of Kenosha Street, one-third mile east of 9th Street.  Part of the property has been previously platted as “Steele-Morrel Center” and part has been platted as “Blocks 1, 2, & 3 Arrow Village Addition.”  According to the applicant, there is a small area between these two plats that is unplatted.  With the Collision Works plat, the applicant is replatting the property.  Some of the existing easements within the Collision Works plat will be vacated by separate instrument.

 

The Planning Commission (4-0 vote) unanimously approved this plat on January 14, 2016. There were no protestants. The Technical Advisory Committee (TAC) reviewed and approved this plat on January 12, 2016.

                     

Cost:                                                                $0

Prepared By:                                           Farhad K. Daroga

Reviewed By:                                          Legal Department
                                    Acting Assistant City Manager

 

Approved By:                      Michael Spurgeon, City Manager

Attachments:                                          1-FAC.BDM.01-04-2015                                   

                                                               2-CHECKLIST.COLLISION WORKS

                                                                         3-CONDITIONAL FINAL PLAT.COLLISION WORKS

                                                               4-CONCEPTUAL SITE PLAN. COLLISION WORKS

Recommendation:

Approve PT15-116, the conditional final plat for Collision Works as recommended by the Planning Commission, Staff and the Technical Advisory Committee (TAC) and in accordance with the attached checklist.

FKD/dl