Broken Arrow Municipal Authority
Meeting of: 05-06-2025
Title:
title
Approval of and authorization to execute Change Order No. 1 with Cherokee Pride for the Melinda Park Water and Sewer Line Rehabilitation Project (S23030)
End
Background:
The Melinda Park Project is to replace the waterline and sewer lines throughout the neighborhood.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Requesting additional days to the contract due to water tie in on Garnett. City crews had issues shutting down the water line and the tie in had to be rescheduled for a later day.
- Obtaining easements from several homeowners took longer than anticipated and caused a delay in the open cutting of the sewer line ditch.
- There is a 74 day change in contract time.
The total cost for Change Order #1 amounts to $0.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $0.00
Total Cost of Change Orders: $0.00
Original Contract Amount: $7,362,860.00
Revised Contract Amount: $7,362,860.00
Percent Change in Contract: 0%
Applicable to Comp. Bid Act: 0%
Cost: $0
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Melinda Park Change Order 1
Recommendation:
recommend
Approve and authorize execution of Change Order No. 1 with Cherokee Pride for the Melinda Park Water and Sewer Line Rehabilitation Project (S23030)
end