Broken Arrow Municipal Authority
Meeting of: 06-1-2026
Title:
title
Approval of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP on-site hypochlorite Generation System Project (2154350)
End
Background:
The Verdigris River Water Treatment Plant On-Site Hypochlorite Generation System will replace an aging Brine tank.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Replace a 48” flow meter at the raw water project.
Total time added to contract is:
- 28 weeks for procurement.
The total cost for Change Order #1 amounts to $98,322.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $98,322.00
Total Cost of Change Orders: $98,322.00
Original Contract Amount: $1,092,000.00
Revised Contract Amount: $1,190,322.00
Percent Change in Contract: 9.00%
Applicable to Comp. Bid Act: 9.00%
Cost: $98,322.00
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: PCO1 48 Inch Mag Meter
Recommendation:
recommend
Approval of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP on-site hypochlorite Generation System Project (2154350)