Approval of and authorization to execute Work Order WO-08, Contract for Cold Milling Asphalt Streets (Bid # 16.141) for the repair of asphalt streets of Lancaster Park I & II, Phase II
.End
Background:
To assist the Streets and Stormwater Department in their street maintenance program with full width Cold Milling for preparation for asphalt repairs. Work Orders utilizing the priced bid items within the contracts are issued to assist the Streets and Stormwater Department with their street maintenance work.
This work order, WO-08, is in the amount of $29,606.20, and is for 15,582.21 square yards of full width 2” cold milling in Lancaster Park I and II, Phase 2. This work is a part of needed maintenance work for our City Streets.
Funding for this work order has been appropriated and is available in the Sales Tax Capital Improvement fund in the amount of $394,000. (Project ST1809, Acct. No. 043-5300-431.70-15)
Cost: $29,606.20
Prepared By: Chuck Williams, Director of Streets and Stormwater
Reviewed By: Finance Department
Legal Department
Assistant City Manager of Operation
Approved By: Michael L. Spurgeon, City Manager
Attachments: Work Order WO-08
Recommendation:
Approve and authorize execution of WO-08, Contract for Cold Milling Asphalt Streets (Bid # 16.141) for the cold milling for the repair of asphalt streets of Lancaster Park I and II, Phase 2.