Broken Arrow City Council
Meeting of: 03/18/25
Title:
title
Approval of and authorization to execute agreement for a public and private partnership to construct a storm sewer at Lynn Oaks Apartments with MACO Construction, Inc. (Project No. SW25100)
End
Background:
Lynn Oaks Apartments are located at 1301 N 6th Street, Broken Arrow. MACO Construction, Inc. is the private contractor constructing the Apartment complex.
During the course of construction an unknown storm sewer was discovered. The storm sewer was connected to the system on Madison St. and an adjacent apartment complex. The storm sewer is located on the west portion of the Lynn Oaks Aparments and the intended outlet is north of the property along the Broken Arrow Expressway. The outlet of the storm sewer system was mostly blocked and causes water to pond on Madison Street. The storm sewer needs to be replaced to operate correctly.
Lynn Oaks Apartments original design included a 30-inch storm sewer system from a new inlet along Madison St through their property and daylighting on the north side. The new inlet is not designed to be connected to a City storm sewer system.
The City worked with the owners of Lynn Oaks Apartments and MACO Construction to design a new storm sewer system along Madison for the mostly blocked system on their property. This new system is designed to connect to the new inlet along Madison St and Lynn Oaks' storm sewer. The Lynn Oaks storm sewer was also increased in size to accept the addition flow. This upgrade will enable the storm water to flow more efficiently and reduce ponding along Madison St.
This contract is with MACO Construction, Inc. for the construction of the storm sewer in the Right of Way along Madison St to be paid for by the City of Broken Arrow and for the construction of the storm sewer at the Lynn Oaks Apartments. MACO is paying for the original design and is requesting the City pay for the difference in the increased storm sewer size in the Lynn ...
Click here for full text