Broken Arrow Municipal Authority
Meeting of: 01-20-2026
Title:
title
Approval of lowest responsible bid to Cherokee Pride Construction, Inc. and authorization to execute a construction contract for the County Line Trunk Sewer Manhole Replacement-Phase IIIB Improvements-Washington St. to Houston St. (Project No. S.22060)
End
Background:
Phase IIIB of the County Line Trunk Sewer stretches from Washington Street north Houston Street. This phase of the Trunk Line has concrete manholes that are severely degraded and are in need of replacement. The design calls for the replacement of 17 manholes in this section. The replacement of these manholes should also reduce odor in the area.
This project was advertised on December 11th and December 18th, 2025. An optional Pre-Bid Meeting was held virtually on December 15th, 2025. There were four (4) bids received on January 8th, 2026. The Certified Bid Tabulation is attached. The lowest responsible bid was Cherokee Pride Construction, Inc. for a Base Bid of $540,010.00. The Engineer’s Estimate was $982,784.00.
Cost: $540,010.00
Funding Source: OWRB Loan
Requested By: Charlie Bright, P.E., Director of Engineering & Construction
Approved By: City Manager’s Office
Attachments: 20260113-Certified Bid Tabulation-County Line Phase IIIB.Executed-S.22060
Recommendation:
recommend
Award the lowest responsible bid to Cherokee Pride Construction, Inc. and approve and authorize execution of a construction contract for the County Line Trunk Sewer Manhole Replacement-Phase IIIB Improvements-Washington St. to Houston St.(Project No. S.22060)