Broken Arrow Municipal Authority
Meeting of: 12-03-2024
Title:
title
Award the lowest responsible bid to Cook Consulting, LLC and approve and authorize execution of a construction contract for the BA Creek Trail Phase II Waterline Relocation Bore Segment (Project No. WL23040)
End
Background:
This project consists of placement of approximately 160 linear feet of 8-inch waterline, of which approximately 130 linear feet will be bored and cased under New Orleans Street on the West side of South 1st Place. The construction time for this project is Ninety (90) calendar days.
The project was advertised on October 31st and November 7th, 2024. An optional Pre-Bid Meeting was held virtually on November 14th, 2024. There were three (3) bids received on November 21st, 2024. The Certified Bid Tabulation is attached. The lowest responsible bid was Cook Consulting, LLC. for a Bid of $99,080.81. The Engineer’s Estimate for the Bid is $239,512.90.
Cost: $99,080.81
Funding Source: OWRB Loan
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: BA Creek Trail Phase II Waterline Relocation Bore Segment Certified Bid Tabulation
Recommendation:
recommend
Award the lowest responsible bid to Cook Consulting, LLC and approve and authorize execution of a construction contract for the BA Creek Trail Phase II Waterline Relocation Bore Segment (Project No. WL23040)
end