Ratify the acceptance of and authorization to accept the Change Order No. 1 for the Lynn Lane Wastewater Treatment Plant Sludge Thickener Pump Replacement with Crossland Heavy Contractors, Inc. (2354180)
End
Background:
The LLWWTP Sludge Thickener Pump Replacement project started in FY 2024 but had along lead time on the pumps. The pumps and some valves finally arrived 22 September 2025.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Request for days due to procurement lead time on the sludge thickener pumps. The days requested are 343 days.
The total cost for Change Order #1 amounts to $0
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $0
Total Cost of Change Orders: $0
Original Contract Amount: $219,325.00
Revised Contract Amount: $219,325.00
Percent Change in Contract: 0%
Applicable to Comp. Bid Act: 0%
Cost: $0
Funding Source: OWRB Loan
Requested By: Charlie Bright, P.E., Engineering and Construction Director
Approved By: City Manager’s Office
Attachments: Change Order 1 LLWWTP Sludge Thickener
Recommendation:
recommend
Accept the Change Order #1 for the Lynn Lane Wastewater Treatment Plant Sludge Thickener Pump Replacement with Crossland Heavy Contractors, Inc. (2354180)