Title: Presentation of proposed lane closure on 23rd Street bridge between Albany Street and Omaha Street
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 11-16-2026

Title:
title
Presentation of proposed lane closure on 23rd Street bridge between Albany Street and Omaha Street
End

Background:
The 23rd Street Improvements Project is currently under construction and is being administered by the Oklahoma Department of Transportation (ODOT) due to the federal funding associated with the project.
The construction phasing plan requires one lane of traffic to remain open in each direction on both the roadway and the existing bridge while bridge construction and roadway widening activities occur simultaneously. The original plans called for saw-cutting portions of the existing bridge deck for partial removal following the installation of temporary bracing and barrier wall systems.
During preparation for the temporary bracing installation, the contractor expressed concerns that saw-cutting operations could further deteriorate the existing bridge deck and potentially create unsafe conditions for the traveling public. The design consultant, contractor, and ODOT construction representatives jointly inspected the bridge and agreed that an alternative approach was necessary.
As a result, a revised temporary bracing system and temporary barrier wall configuration were developed. Installation of this modified system requires a temporary closure of the northbound lane. This closure is necessary to ensure the safety of both the traveling public and construction personnel during the installation process.
The exact dates for the proposed lane closure are to be determined. Staff will work with the ODOT inspection firm and the contractor to choose dates and times in an effort to minimize traffic impacts.
During the closure period, northbound traffic will be detoured around the bridge, while southbound traffic will remain open throughout the corridor. Advance notification will be provided to the public and nearby businesses. Variable message boards will be installed to inform motorists of the upco...

Click here for full text