Broken Arrow Municipal Authority
Meeting of: 07-14-2025
Title:
title
Approval of and authorization to execute Change Order No. 1 with Scissor Tail Construction LLC for the Broken Arrow Public Safety Complex Fire Department Annex Building Project (191711)
End
Background:
The BAPSC Fire Department Annex Building project is to renovate the existing facility for the Fire Department. This project will add 7 Ambulance bays allowing for the quick resupply of all Ambulances throughout the City of Broken Arrow.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Requesting additional days due to the complexity of the project, many differing site conditions, and omissions that are causing delays. The original time to complete the project was not enough due to the differing site conditions and omissions that are adding more to the project.
- There is a 79-day change in contract time.
The total cost for Change Order #1 amounts to $0.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $0.00
Total Cost of Change Orders: $0.00
Original Contract Amount: $939,153.28
Revised Contract Amount: $939,153.28
Percent Change in Contract: 0%
Applicable to Comp. Bid Act: 0%
Cost: $0
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: BAPSC Fire Dept Annex Change Order 1
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Scissor Tail Construction LLC for the Broken Arrow Public Safety Complex Fire Department Annex Building Project (191711)