Broken Arrow City Council
Meeting of: 05-06-2025
Title:
title
Consideration, discussion and possible award of the lowest responsible bid to Scissor Tail Construction for the Renovation of the Public Safety Complex - EMS Building (Project Number 191711)
End
Background:
The Engineering and Construction Division has solicited bids for the Renovation of the Public Safety Complex - EMS Building (Project Number 191711). The renovation will adapt the existing annex building in the Public Safety Complex for the use of the EMS team to service and appropriately store the City of Broken Arrow’s Ambulances.
The project was advertised for two consecutive weeks and followed the 21-day bidding process. Two bids were received and opened on April 3, 2025. The bids included a base bid and three alternatives. The lowest responsible bid was from Scissor Tail Construction with a base bid of $939,153.28, the alternatives are not awarded. The Engineer’s Estimate was $846,383.25.
Cost: $939,153.28
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, P.E., Director of Engineering & Construction
Approved By: City Manager’s Office
Attachments: BAPSC Fire Department Annex EMS Building - Bid Tab
Recommendation:
recommend
Award the lowest responsible bid to Scissor Tail Construction for the Renovation of the Public Safety Complex - EMS Building (Project Number 191711)
end