Skip to main content
LEGISLATIVE RESEARCH CENTER
File #: 24-1075    Name:
Type: Consent Item Status: Agenda Ready
File created: 8/5/2024 In control: Broken Arrow City Council
On agenda: 9/3/2024 Final action:
Title: Approval of and authorization to execute Amendment Number 2 to Agreement for Professional Consulting Services with Benham Design, LLC for the 23rd Street Widening from Albany Street to Omaha Street and Bridge Replacement (ST1931&1932)
Attachments: 1. Amendment No. 2 - ST1931 for 9-3-24 Council Agenda
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 09-03-2024

 

Title:

title

Approval of and authorization to execute Amendment Number 2 to Agreement for Professional Consulting Services with Benham Design, LLC for the 23rd Street Widening from Albany Street to Omaha Street and Bridge Replacement (ST1931&1932)

End

 

Background:

The 23rd Street Widening from Albany Street to Omaha Street Project (ST1931&1932) is being designed by Benham Design, LLC and is a named 2018 GO Bond, Transportation Project.  As part of the original contract scope, the City and consultant designed for the widening of 23rd Street from Albany Street to Omaha Street with a Bridge Replacement.  During the project development, $3 million of Surface Transportation Program (STP) funding has been approved and programmed for this project, which requires the Oklahoma Department of Transportation (ODOT) to conduct the bidding process.  The Engineering & Construction Department recommends amending the original contract with Benham Design, LLC for the amount of $154,150.00 to revise the design deliverables to standard ODOT bidding format requirements, prepare the 404 permit application, update the survey to show acquired right-of-way, and update the RWD4 waterline relocation at the north limits of the project.

 

Cost:                                                                $154,150.00

Funding Source:                     2018 GO Bond

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Amendment No. 2

Recommendation:

recommend

Approve and authorize execution of Amendment Number 2 to Agreement for Professional Consulting Services with Benham Design, LLC.