Approval of and authorization of Final Acceptance for the public improvements at Broken Arrow Public Schools Events Center located at 1901 East Albany Street
End
Background:
Timber Wolf Excavating, LLC has completed the construction for Broken Arrow Public Schools Events Center project. The required improvements are in accordance with approved construction plans and appropriate construction documents. These improvements have been constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvements are for the water installations.
The owner desires to donate the public improvements identified above to the City of Broken Arrow. These improvements have an approximate value of $128,050.00
Cost: None
Funding Source: N/A
Requested By: Ethan JL Edwards, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: COBA Infrastructure Inventory - BAPS Events Center
Recommendation:
recommend
Approve and authorization for final acceptance and donation of the public improvements at Broken Arrow Public Schools Events Center located at 1901 East Albany Street