Approval of and authorization to execute Change Order #1 with Scissor Tail Construction LLC for the Grain Silo Improvements project (2417300)
End
Background:
The Grain Silo Improvements project will repaint the outside of the grain silo.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Remove and demo gates, exterior ladder, and landing on Silo; Paint newly installed conduit same color as body of silo; Paint garage doors same color as body; Railroad Safety Training for Scissortail and subs; Replace walk door and add security locks; and add a stencil for additional logo
- There is a 5-day change in contract time.
The total cost for Change Order #1 amounts to $21,108.20
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $21,108.20
Total Cost of Change Orders: $21,108.20
Original Contract Amount: $169,938.00
Revised Contract Amount: $191,046.20
Percent Change in Contract: 12.42%
Applicable to Comp. Bid Act: 12.42%
Cost: $21,108.20
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: COBA SILO CO signed
Recommendation:
recommend
Approve and authorize execution of Change Order #1 with Scissor Tail Construction LLC for the Grain Silo Improvements project (2417300)