Title: Award of the lowest responsible bid to Gober Construction, LLC and approve and authorize execution of a construction contract for Concrete Panel Replacement Street Repair - Turtle Creek Phase 2 (ST23030)
Attachments: 1. ST23030 - Bid Tab - Concrete Panel Street Repair - Turtle Creek Phase 2
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 12-03-2024

 

Title:

title

Award of the lowest responsible bid to Gober Construction, LLC and approve and authorize execution of a construction contract for Concrete Panel Replacement Street Repair - Turtle Creek Phase 2 (ST23030)

End

 

Background:

Design for the Concrete Panel Replacement Street Repair for the Turtle Creek subdivision has been completed and Engineering and Construction Department staff worked with the design consultant to prepare construction documents for letting. The project includes the removal and rehabilitation of approximately 5,700 square yards of concrete roadway panels along with miscellaneous concrete work including sidewalk, curb, sewer, and ADA ramps. This roadway reconstruction will be located in the Turtle Creek subdivision on the northwest corner of W. Houston Street & S. Elm Pl.

The project was advertised for bids on November 5, 2024, and November 12, 2024.  Bids were opened on November 26, 2024, and seven (7) bids were received. The Certified Bid Tabulation is attached. The bids submitted were composed of seventeen (17) pay items.

The lowest responsible bid was submitted by Gober Construction, LLC for $525,489.00. The engineer’s estimate was $750,609.00.

 

Cost:                                                                $525,489.00

Funding Source:                     Street Sales Tax

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Certified Bid Tabulation

 

Recommendation:

recommend

Award the lowest responsible bid to Gober Construction, LLC and approve and authorize execution of a construction contract for Concrete Panel Replacement Street Repair - Turtle Creek Phase 2 (ST23030). 