Title: Acknowledgement of receipt of Oklahoma Department of Environmental Quality (ODEQ) Permit No. WL000072240691 for construction of the New Elevated Storage Tank in South Broken Arrow (Project No. 165424)
Attachments: 1. ODEQ Permit for New EST in South BA
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of: 11-05-2024

 

Title:

title

Acknowledgement of receipt of Oklahoma Department of Environmental Quality (ODEQ) Permit No. WL000072240691 for construction of the New Elevated Storage Tank in South Broken Arrow (Project No. 165424)

End

 

Background:

Plans and Specification were submitted to ODEQ on August 15, 2024. The plans were approved. The permit to construct was signed on September 13, 2024, and received on October 23, 2024.

 

Cost:                                                                $0

Funding Source:                     N/A

Requested By:                      Charlie Bright, P.E., Director of Engineering & Construction

Approved By:                      City Manager’s Office

Attachments:                                          ODEQ Permit to Construct New Elevated Storage Tank in South Broken Arrow

 

Recommendation:

recommend

Acknowledgement of receipt of Oklahoma Department of Environmental Quality (ODEQ) Permit No. WL000072240691 for construction of the New Elevated Storage Tank in South Broken Arrow (Project No. 165424).

end