Broken Arrow City Council
Meeting of: 12-02-2025
Title:
title
Approval of and authorization to execute the Change Order No. 2 with Paragon Contractors, LLC for the Jasper Street & Aspen Intersection Improvements (ST2031)
End
Background:
The Jasper Street and Aspen Intersection project is to widen the intersection and mill and overlay Aspen from Jasper to Shreveport.
Change Order #2 addresses the following additions/deletions/changes to the contract:
- Removal of Pecan Tree NW Corner of Jasper and Aspen Ave
- Remobilization of Milling Machine due to Soccer Tournament
- There is a 5 day change in contract time.
The total cost for Change Order #2 amounts to $13,286.35
The additional cost associated with these changes is as follows:
Previous Change Orders: $13,568.27
This Change Order(s): $13,286.35
Total Cost of Change Orders: $26,854.62
Original Contract Amount: $2,373,118.11
Revised Contract Amount: $2,395,506.73
Percent Change in Contract: 0.94%
Applicable to Comp. Bid Act: 0.94%
Cost: $13,286.35
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: CO 02 Shreveport intersection modifications
Recommendation:
recommend
Approve and authorize execution of Change Order #2 with Paragon Contractors, LLC for the Jasper and Aspen Intersection Improvements (ST2031)
end